Commercial Plaza
at old GTS Stand

 

  • Area of site: 39034.55 Sf (7.22 K)
  • Lower Ground 83 Shops
  • Cost of Construction: Rs. 3.95 M
  • Completion time: (One Year) Febuary 2013
  • COMPLETED BEFORE TIME January 2013

 


Jinnah Complex

 

  • Area: 30389.65 SFt (5.58 Kanals)
  • Lower Ground 42 Shops
  • Cost of Construction: Rs. 40 M
  • Completion time: (6 Months) Jun 2014

 


Picture to Uploaded
 
 

Shops at Kohat Road

 

  • Area: 17600 SFt (3.23 Kanals)
  • Lower Ground 50 Shops
  • Ground Floor 50 Shops
  • Cost of Construction: Rs. 48.5 M
  • Completion time: Starting April 2018 (8 Months)... Under Construction...

 


 

Contact Persons

Mr. ---------------------,  Cantt Overseer (CO) - 0111-11111111
Mr. Awais Muhammad, Works Supervisor - 0332-9739636